2005 projects
Since 2005, the serial steel hull section building for great containerships is carried out. 9000 tons of blocks were built in 2005. Up till May 29, 6411 tons of them were built.
|
Luxury motor yacht "Water Lily" |
|
|
client: |
"Aarhus Vaerft AS", Denmark. |
|
|
length (m): width (m): |
43.50 9.02 |
completion: |
2006-01 |
|
|
160 t of steel and 26 t of aluminum involved in the hull building. The value of works carried out 1,1 million EUR. |
|
Passenger and car ferry |
|
|
client: |
"Fiskerstrand Verft AS", Norway. |
|
|
length (m): width (m): |
109.00 16.80 |
completion: |
early in 2006-01
|
|
|
1350 t of steel involved in the passenger and car ferry hull project that lasted almost 7 months. The cost of works carried out – 3,5 million EUR. |
|
The yacht "Caneli" |
|
|
client: |
"Aarhus Vaerft AS", Denmark. |
|
|
completion: |
early in 2006 |
|
|
Yacht hull building. 140 t of steel and 30 t of aluminum involved in the building, the cost of works carried out is app. 1,2 million EUR. The Klaipedians installed propulsion and auxiliary engines, steering mechanisms, the main control panel, and the yachts will be completed by the customers themselves in Denmark. |
|
Offshore yacht "Amante" |
|
|
client: |
"Aarhus Vaerft AS", Denmark. |
|
|
length (m): width (m): |
44.40 9.00 |
completion: |
2005 year |
|
Offshore yacht hull building. 140 t of steel and 25 t of aluminium involved in the building. |
|
Hull building for a ferry |
|
|
client: |
Fiskerstrand Verft AS. |
|
|
length (m): width (m): weight (t): |
88.16 16.10 1200 |
begining: completion: |
2004-05-26 2005-03-22 |
|
Propulsion engines 2x Caterpillar 3508, speed – 14 knots. |